San Pablo Avenue Complete Streets Project - Weekly Updates(10/29/18)

Work Completed This Week

GBI continued with construction of median area and continued with construction of the roadway section in the inside lanes north of Robert Miller Drive.  

RE Maher continued with median curb north of Robert Miller Drive. &am...

Read on...

Public Works - Engineering
Posted on: October 22, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(10/22/18)

Work Completed This Week

GBI switched traffic on San Pablo Avenue from Robert Miller Drive north, shifting traffic to the outside lanes and closing the inside lanes adjacent to the median. 

GBI paved sections of the median area and continued with c...

Read on...

Public Works - Engineering
Posted on: October 15, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(10/15/18)

Work Completed This Week

GBI is continuing with roadway section north of Robert Miller and completing drainage systems.  

RE Maher is continuing with median curb north of Robert Miller Drive.  

MBE is working on foundations for light poles ...

Read on...

Public Works - Engineering
Posted on: October 8, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(10/08/18)

Work Completed This Week

GBI continued work on roadway section north of Robert Miller and continued with drainage systems. 

RE Maher working on the J-Ditch above the soil nail wall.  They are also working on median curb north of Robert Mil...

Read on...

Public Works - Engineering
Posted on: October 1, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(10/01/18)

Work Completed This Week

GBI continued work on roadway section north of Robert Miller and continued with drainage systems. 

RE Maher continued work on retaining wall A.

MBE is back on site working of street lighting north of Robert Miller.

Work Forec...

Read on...

Public Works - Engineering
Posted on: September 24, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(9/24/18)

Work Completed This Week

GBI continued work on roadway section north of Robert Miller and completing drainage systems. 

RE Maher continued work on retaining wall A.

Work Forecast for Next Week

GBI will continue with roadway section north of Robert Mi...

Read on...

Public Works - Engineering
Posted on: September 17, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(9/17/18)

Work Completed This Week

GBI is working on the roadway section north of Robert Miller in front of the completed soil nail wall.  They are also completing excavation and grading for retaining wall A at the northeast side of Rivers.  

RE Mah...

Read on...