Circle S Site Concept and Regulating Plan Timeline
AUGUST 9, 2011 UPDATE
Unless noted, all deadlines are in 2011. PDF Format
Go back to project page.
Keep me informed
Our new website provides you with the opportunity to register for news and updates in two ways:
Unless noted, all deadlines are in 2011. PDF Format
Task | Action | Description | Participants | Deadline |
---|---|---|---|---|
Task 1 |
Joint Study Session Planning Commission and City Council |
The CDC will present site redevelopment concept for Circle S and will discuss strategies for entitlement and implementation. We will prepare materials for a brief gallery to allow members of the Council, Commission, and general public suggest ideas for site development. |
City Council |
Mar 7 |
Task 2 | Subcommittee Meeting to review comments received at the March Study Session |
The CDC will meet with the Circle S Subcommittee to discuss the comments received at the Study session and refinements made to the Conceptual Plan based on this initial round of input. |
Circle-S Subcommittee |
May 11 |
Task 3 | Study Session with Planning Commission and City Council #2 |
The CDC will present a site design that incorporates the comments that were received at the March 7, 2011 joint City Council and planning Commission session. A brief gallery session will be held to allow members of the Council, Commission, and general public review the changes made. | City Council Planning Commission General Public |
July 5 |
Task 4 | Preliminary ‘check-in’ with Development Community and stakeholders | The CDC will meet with members of the development community and key stakeholders to solicit their feedback about the development code’s required elements. We will fine-tune the code to reduce identified obstacles to implementation. |
Development Community |
Aug 29 |
Task 5 | Meeting with Subcommittee to Present the Draft Development Code | The CDC will meet with the Circle-S Subcommittee to present and discuss a draft Regulating Code. CDC will prepare high-quality graphic hand-outs for each member to retain and review. The CDC will then modify the draft code based on input from Staff and the Subcommittee. |
Circle-S subcommittee |
Early Sept |
Task 6 | Kick-off CEQA process | The draft code will form the basis of the CEQA process. A 45-day public review period will be required. |
Public comment period |
Mid-Sept |
Task 7 | Community meeting/ Study Session with City Council and Planning Commission | The CDC will present the Draft Regulating Plan and CEQA study to the Council, Commission, and general public for input. |
City Council |
Late Sept |
Task 8 | Public hearing to recommend adoption by the Planning Commission | Public hearing for review of the Plan and associated CEQA documents for adoption. The Planning commission will consider making a recommendation to the council for approval. |
Planning Commission |
Early Oct |
Task 9 | Public Hearing for adoption by the City Council | Final Public hearing for review of the Plan and associated CEQA documents for adoption. |
City Council |
Late |
Go back to project page.
Keep me informed
Our new website provides you with the opportunity to register for news and updates in two ways:
- Register to receive specific information, or
- Sign up for regular updates from the City Manager.