News Flash

News Flash

News Flash

News Flash

News Flash

Posted on: August 14, 2018

Where's Pablo?

Pablo 300

Pablo, the San Pablo Police Department’s mascot, continues to make a splash in the community. From August 20th through September 30th, more than 20 participating San Pablo businesses will place cardboard cutouts of Pablo in their stores and fami...

Read on...

Details here! Home News Example
Posted on: August 9, 2018

Senior Center Services and Paratransit Announce Location Changes

Senior Center 300

The Senior Center will be under construction between through October 13, 2018. Many programs and services will be relocated to various sites to accommodate the community.  For more information please contact Senior Services offices at (5...

Read on...

Additional Info... Home News Example
Posted on: March 6, 2018

California Minimum Wage Law 2018

COSP City of New Directions 300

Effective January 1, 2018, the minimum wage in San Pablo is $10.50 per hour for employers with 25 or fewer employees, and $11.00 per hour for employers with 26 or more employees.  The City of San Pablo defaults to the state law because it does no...

Read on...

Additional Info... Home News Example

News Flash

News Flash

News Flash

News Flash

Posted on: September 3, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(9/3/18)

Work Completed This Week

GBI continued with drainage systems and soil removal and grading.  They also graded for curb and gutter on the east side of San Pablo Avenue and finish excavation for retaining wall A.

RE Maher continued with curb, gutter, ...

Read on...

Public Works - Engineering
Posted on: August 27, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(8/27/18)

Work Completed This Week

GBI continued with drainage systems and grading for curb and gutter on the east side of San Pablo Avenue.  

RE Maher continued with curb, gutter, and sidewalk on the west side of San Pablo Avenue. 

AVAR continued wi...

Read on...

Public Works - Engineering
Posted on: August 20, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(8/20/18)

Work Completed This Week

GBI is working on drainage systems.  They are also excavating retaining wall A and grading for curb, gutter, and sidewalk on the east side of San Pablo Avenue 

RE Maher is continuing with curb, gutter, and sidewalk...

Read on...

Public Works - Engineering
Posted on: August 13, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(8/13/18)

Work Completed This Week

GBI started with grading for curb and gutter on the east side of San Pablo Avenue.  They also started work on drainage systems.  

RE Maher will complete reinforcing steel and placing concrete for retaining Wall B. ...

Read on...

Public Works - Engineering
Posted on: August 6, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(8/6/18)

Work Completed This Week

GBI excavated for the retaining walls B.  They also started work on the storm drain systems.  They also continued with grading for curb, gutter, and sidewalk on the west side of San Pablo Avenue. ...

Read on...

Public Works - Engineering
Posted on: July 30, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(07/30/18)

Work Completed This Week

GBI excavated for the retaining walls B.  They also started work on the storm drain systems.  They also continued with grading for curb, gutter and sidewalk on the west side of San Pablo Avenue. 

GBI start...

Read on...

Public Works - Engineering
Posted on: July 23, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(07/23/18)

Work Completed This Week

GBI continued with grading for the retaining walls A and B.  They also continued with grading for the new curb, gutter and sidewalk on the west side of San Pablo Avenue from Rivers to Robert Miller.  GBI also clea...

Read on...

Public Works - Engineering
Posted on: July 16, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(07/16/18)

Work Completed This Week

Ghilotti Brothers, Inc. (GBI), the prime contractor for the project, started excavation and material removal for installation of retaining walls A and B.  GBI also ground down the existing asphalt pavement road surface alo...

Read on...

Public Works - Engineering
Posted on: July 9, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(07/09/18)

Work Completed This Week

Ghilotti Brothers, Inc. (GBI) placed asphalt pavement within the new extended turn pocket at the Rivers Street and San Pablo Avenue intersection and along the east side of San Pablo Avenue north of La Puerta Road within the widened...

Read on...

Public Works - Engineering
Posted on: July 2, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(07/02/18)

Work Completed This Week

Ghilotti Brothers, Inc. (GBI) continued with excavation and construction of roadway structural section along the east side of San Pablo Avenue north of La Puerta Road.  GBI also installed new pavement in San Pablo Avenue n...

Read on...

Public Works - Engineering
Posted on: June 25, 2018

San Pablo Avenue Complete Streets Project - Weekly Updates(06/25/18)

Work Completed This Week

Ghilotti Brothers, Inc. (GBI) continued with excavation and construction of roadway structural section along the east side of San Pablo Avenue north of La Puerta Road.   Also, GBI provided construction support to subcontra...

Read on...